Part 4
Testing the MeeFog system.
The river was partially filled to allow for early testing of the pumps and other water-related systems.
Shortly after, the river was completely filled for the first time in months.
River traffic did not reopen yet as this was still a construction zone.
The test and adjust phase reveled a problem with the gas lines, necessitating a complete drain of the river.
In this picture, you can see each of the light/fountain platforms.
Staining of the cider mill has begun, and rock work is almost complete.
The center fountain platform is in the show position, and the Pinocchio puppets are up.
If you look closely, you can see that they were testing the fountains on the right.
At this point in the construction process, some river traffic had reopened. This shot from the Mark Twain shows the composition of the original fountain hardware.